Waconia Clinic Expansion
Main Entrance Reopening - February 9th
The clinic will remain open for the entirety of the project.
Lakeview in Waconia will be building out the empty space in the westernmost section of our building in 2025 & 2026. In addition will will be renovating our registration and waiting areas, updating the front facade of the building and improving our parking lot!
Patient Parking Lot Reopening – February 9th
Patients can begin utilizing the main parking lot where parking was located prior to our construction project. (See map below.) They can then proceed to the new main entrance on the south facing side of the building.
Waconia Pharmacy:
The existing pharmacy door will remain open for PHARMACY customers. Parking for Waconia Pharmacy customers is available in the lot west of the building. (See map below.)
Patient Drop Off & Handicap Access
Patients needing to be dropped off for appointments can do so at the new main entry. (See map.)
Handicap parking is available near the front entry. More handicap parking (adjacent to the front entry sidewalk) will become available when facade renovations are complete.
Building Entrance – Main Entry Reopens February 9th
Patients should begin entering our building via the new patient entrance on the south facing side of our building. (See map below.) Once inside patients can check in via the partially completed registration desk or the kiosks. Staff will be available at all time to direct patients.
Parking Map
As of February 9th, 2026
Project Timeline (projected)
- Main Parking Lot Construction: 9/22/25 – 10/5/25 – Complete
- Entrance & Facade Renovation: 10/3/25 – 12/11/25
- Main Entry Reopen: 2/9/26
- Interior Renovation & Build Expanded Women’s Health Services Area – 11/10/25 – 3/18/26
- Pharmacy Renovation – projected for January, 2026
- Project Completion: Late March – Early April, 2026.